Club Update

Court Refurbishment – Day 9

The previously punched drainage holes have been filled with shingle.
The new post sockets and net anchors have been installed.
The cut edge of the existing surface has been prepared for tarmac.
A bitumen tack-coat has been sprayed over the entire surface.
The new kerbing has been installed between courts 3&4.

The preparatory work is almost complete however, it must now pause due to Covid-19 restrictions.  Work will resume as soon as restrictions are lifted.

Also, new fascia, guttering and downpipe has been fitted to the clubhouse.